Client
Tallgrass -
Construction Manager
Bechtel Corporation / Tallgrass
Highlights
- 400,000 CY – Cut & Fill
- 1,200,000 CY – Cut & Stockpile
- 350,000 CY – Stripping Topsoil
- 3,600,000 SF – Site Grading
Summary
This mission-critical project involved our pre-construction team producing cost-budget analyses for a variety of construction processes while producing schedule impacts for each considered option. Wagner also participated in constructability reviews including BIM modeling. Operations worked closely with project management on site coordination of other trades along with quality control and survey.