Highlights
  • 7,000 CY of cast-in-place concrete
  • Construction of stormwater lift station and new intake structure
  • Installation of 3,700 LF of storm sewer pipe ranging from 15″ to 60″
  • 85,000 CY of structural and mass excavation
  • Installation of 3,400 LF of new large diameter ductile iron water mains ranging from 12″ to 30″
  • Connections to an existing 54″ fiberglass reinforced pipeline.
Summary

The scope of the project was to construct a reinforced concrete floodwall and reroute underground utilities around the existing water treatment plant to protect the plant from flood conditions. The project posed the unique challenge of working next to the Mouse River. A high water table required expert dewatering and excavations 30’ deep. Maintaining water supply to the plant while installing new intake and treated water lines was critical.

Dirt lot before tall concrete wall, three trees and blue sky.
Yellow bulldozer moves dirt next to tall concrete wall.
Excavator sets rocks by riverbank on a sunny day.
Dirt lot with tire tracks, brick wall, and curved curb.
Dirt mound by red brick wall, tire tracks visible, cloudy sky.